When preparing a claim for an extension of time, the party making the claim bears the responsibility to provide proof. The claimant must identify the events that caused the delays and explain how these events affected the timeline for achieving practical or substantial completion. Delays may arise from contract variations issued by the employer or […]
On 3 July 2023, the Irish Government announced significant risk-related amendments to the suite of Irish Public Works contracts. One potential major issue for contracting authorities is the ‘provision whereby the liability of a contractor to the Employer will be limited to a monetary amount (“the Liability Cap”). In its guidance note to contractors and […]